Solar documents
Permits, connection, station registration
Details
Building permit
Rooftop/facade PV — no permit up to 30 kW; ground-mounted — declaration/permit by area.
Connection terms
DSO technical terms: capacity, connection point, meter — for selling and backup.
Act & meter
A bidirectional meter + commissioning act — the basis for net billing/green tariff.
Contract
Electricity purchase agreement with the supplier — filed with the act and station diagram.
The order is critical: connection terms → install → meter → act → contract. Selling power without a commissioning act is illegal; a 'for-self' station without connection terms can't legally tie to the grid.