Solar documents

Permits, connection, station registration

Details

  • Building permit

    Rooftop/facade PV — no permit up to 30 kW; ground-mounted — declaration/permit by area.

  • Connection terms

    DSO technical terms: capacity, connection point, meter — for selling and backup.

  • Act & meter

    A bidirectional meter + commissioning act — the basis for net billing/green tariff.

  • Contract

    Electricity purchase agreement with the supplier — filed with the act and station diagram.

The order is critical: connection terms → install → meter → act → contract. Selling power without a commissioning act is illegal; a 'for-self' station without connection terms can't legally tie to the grid.