Gas Equipment

Appliance → placement norms and required documents

Placement norms

  • •Min boiler room volume: ≤30 kW — 7.5 m³, 30–60 kW — 13.5 m³, 60–200 kW — 15 m³
  • •Ceiling ≥ 2.5 m
  • •Easily-reset glazing ≥0.03 m² per 1 m³
  • •Supply air: 3× air exchange + combustion air
  • •Door with grille/gap ≥0.02 m²

Documents

  • •Gas supply project (from gas distribution company)
  • •Technical conditions for connection
  • •Tie-in/gas-start act
  • •Boiler passport + service contract
  • •Annual chimney/ventilation check protocol

Norms are generalized (based on DBN/DSTU gas system rules). Coordinate the project with the gas distribution company before installation — unauthorized tie-in or relocation is penalized by disconnection.