Mini-plant economics
Raw material → product: yield, costs, processing margin
Parameters
On-farm processing — milk to cheese/yogurt, grain to flour, berries to dried. Cheese yield from milk ~10–12% (8–10 l per kg), yogurt ~90%. Processing margin = yield × product price − raw material − plant costs. Threshold: minimum volume for equipment payback. Own raw material's opportunity cost (selling it raw) is also a cost — count it honestly.
Shift economics
- Product
- 55.0 кг
- Revenue
- 24 750 грн
- Raw cost
- 6 000 грн
- Processing margin
- 16 250 грн